Roadworks
Road Maintenance
The Shire's 2008/09 budget includes $1.1 million for road maintenance works, which includes general road maintenance, grading of gravel roads, slashing of roadside trees in rural areas, edge patching and slashing / spraying of road verges. If you identify a maitenance requirment, please click here to complete a Roadworks Request Form. Please note that road grading is dependent on weather conditions and cannot necessarily be carried out when requested.
Road Construction
The construction and maintenance of roads take a large portion of the Shire's budget, usually equivalent to the amount of rates raised. This year there are a number of programs in place which deal with the long term planning for the maintenance and upgrading of the road network. These include rural road resealing program, rural road reconstruction program and townsite drainage.
The roadworks program is formulated taking into consideration the amount of funding that can be attracted from the Federal and State Governments, to reduce the burden on ratepayers. These programs are developed 1-2 years in advance of the Council setting its annual budget.
Local Government annual budgets take into account anticipated works for the ensuing year and the amount of revenue that is required to meet that commitment. Having established the works programme, the Council is unable to approve additional works during the year unless it deletes works of corresponding value that have been approved in the budget. To meet strict budget preparation deadlines, ratepayers are urged to contact their Councillors before the end of March each year with any requests that they want considered by Council for inclusion in the budget.
The following capital roadworks have been budgeted for 2008/09. While the Shire endeavours to complete all budgeted works, circumstances such as weather, plant breakdown and other unforeseen occurrences do not always allow this to happen. Please see the Budget 2008/09 for full details of all programs.
| Road
|
Section
|
Funding Program
|
Work
|
Budget Amount
|
| Barrow Road
|
Various
|
Roads to Recovery
|
Widen formation and clear tree canopy
|
$55,630
|
| Bevan Road
|
Various locations
|
Council Funds
|
Improve existing formation, drainage and tree lopping.
|
$45,000
|
| Carbarup Road
|
Railway Crossing Area
|
Blackspot
|
Realign intersecting roads, widen, reconstruct & seal
|
$73,448
|
| Carbarup Road
|
Railway to Beverley Road (5km)
|
Roads to Recovery
|
Shoulder upgrade and re-seal
|
$77,000
|
| Coote Street
|
Full length (1.05km)
|
Council Funds
|
Final trim, gravel, prime and seal to 6m
|
$27,361
|
| Eulup-Manurup Road
|
Intersection with Boyup Road
|
Blackspot
|
Realign intersection to 'T' Junction
|
$26,711
|
| First Avenue/ Coote Street Kendenup
|
Intersection with Coote Street
|
Council Funds
|
Spray seal
|
$780
|
| Jones Road
|
SLK 0.0 to SLK 1.0
|
Council Funds
|
Road realignment, widening, pavement and culvert construction
|
$23,020
|
| Kendenup Carpark
|
Car park - 0.65km
|
Council Funds
|
Seal gravel car park opposite shops Kendenup
|
$4,621
|
| Lowood Road
|
Langton Road to Muir Street
|
Council Funds
|
Completion of streetscape works
|
$10,000
|
| Mallawillup Road
|
(6km) From 1km past Boyup Road Intersection
|
Roads to Recovery
|
Shoulder upgrade and re-seal
|
$92,400
|
| Martagallup Tenterden Road - Full Length (PC)
|
Full length - 8.46km
|
Council Funds
|
Upgrade, gravel re-sheet
|
$205,000
|
| Millinup Road
|
SLK OO Woodlands to SLK 3.4
|
Council Funds
|
Clear widen formation and gravel
|
$68,000
|
| Mondurup Street
|
From end of bitumen to culdesac
|
Council Funds
|
prepare gravel base and seal
|
$8,000
|
| Mount Barker - Porongurup Road
|
SLK 12 to SLK 18
|
Regional Road Group
|
Widen pavement, gravel overlay and seal 7m
|
$585,331
|
| Mount Barker Drainage Improvements
|
East Mount Barker drainage catchment
|
Council Funds
|
Improvements to underground drainage systems in the east Mount Barker drainage catchment.
|
$25,000
|
| Mount Barker Footpath Construction
|
Various locations
|
Council Funds
|
Footpath improvements within the Mount Barker townsite
|
$20,000
|
| Pre Construction Future Works
|
Preconstruction Activity - Future Works
|
Council Funds
|
Advance planning, survey, design, and approval of urban and rural road construction projects.
|
$20,000
|
| Quangellup Road
|
Full Length of sealed section (4.78km)
|
Roads to Recovery
|
Shoulder upgrade and re-seal
|
$73,612
|
| Rocky Gully Townsite Drainage Upgrade
|
Drains in townsite
|
Council Funds
|
Upgrade town drainage system
|
$16,000
|
| Spencer Road
|
SLK 00 to SLK 2.16
|
TIRES
|
Narrikup Southern By pass construction 10m formation and seal
|
$930,269
|
| Spencer Road
|
SLK 6 to SLK 8
|
TIRES
|
Widen formation to 10m and seal, land resumptions
|
$300,000
|
| Spencer Road Bypass
|
Albany Highway intersection
|
TIRES
|
Construct Albany Highway slip lanes
|
$150,000
|
| Stothard Road Signage Upgrade
|
Approach to Road
|
Council Funds
|
Signage upgrade
|
$420
|
| Woodlands Road
|
SLK 1.1 to SLK 3.3
|
Council Funds
|
Trim gravel and seal 6m (gravel work completed)
|
$44,300
|
| Woogenellup Road
|
Floodway
|
Blackspot
|
Widen approaches and elevation
|
$321,176
|
| Yellanup Road
|
Start Albany Hwy
|
Roads to Recovery
|
Re-construct, widen and seal to 7m
|
$118,000
|
 |